well, we've been in the place over two weeks now. we have new tables and chairs in the bar area, new refrigeration for the bar, the beginnings of our cold prep layout in place, countertops installed, and nearly everything painted.
Most of the team is hired, too. there are a few spots to fill, most of that will be wrapped up this week.
We are still developing our menu, evening food concepts and wine program. Permits, licensing and red tape are our major hangups at this point. the draught beer may take longer to get installed than we'd like. we did get a 10-tap tower however. I'm behind on the photographings of the porgress [sic].
oh, and some jerk keeps putting superglue in our locks. seriously, knock it off.